24/7 Operations Comparison

Pitman vs Panama vs DuPont Shift Schedules

A technical, mathematical comparison of the three dominant four-crew, 12-hour continuous shift architectures—evaluating rotation speed, turnaround rest, FLSA weekly overtime, and industry fit.

Shared 4-Crew Continuous Baseline

Staffing Model

4 Crews

2 Working / 2 Off Daily

28-Day Duty Load

168 Hours

14 Shifts × 12 Hours

Average Workweek

42.0 Hours

2,190 Scheduled Hrs / Yr

Calendar Days Off

182.5 Days

Exactly 50% of the Year

1. The Shared 672-Hour Continuous Math—And Where They Diverge

Every continuous 24/7 facility faces the same arithmetic constraint: a 28-day (four-week) operational window contains 672 total coverage hours (28 days × 24 hours). Dividing 672 hours across four balanced crews (Crews A, B, C, and D) assigns each crew 168 hours every 28 days—14 twelve-hour shifts and 14 calendar days off, averaging 42.0 hours per week.

While the Pitman, Panama, and DuPont schedules share identical annual hours and headcount budgets, they distribute rest days and circadian transitions in fundamentally different ways:

  • Fixed Pitman (2-2-3 Pattern): Follows a 14-day work/off sequence—2 On, 2 Off, 3 On, 2 Off, 2 On, 3 Off—where two squads work fixed Day shifts (e.g., 07:00–19:00) and two squads work fixed Night shifts (19:00–07:00), rotating only at semi-annual or seniority shift bids.
  • Slow-Rotating Panama (28-Day Biweekly Flip): Uses the exact same 2-2-3-2-2-3 workday cadence as Pitman, but squads rotate from Day shifts to Night shifts every 14 days (2 weeks of Days followed by 2 weeks of Nights), equalizing night burden across all four crews without seniority lockouts.
  • DuPont (28-Day Rapid-Block Cycle): Sequences 4 Nights → 3 Off → 3 Days → 1 Off → 3 Nights → 3 Off → 4 Days → 7 Off. By clustering shifts into 3- and 4-day runs, every crew earns a 7-consecutive-day vacation block every single month with zero PTO deduction.

2. Master Side-by-Side Architecture Comparison

Plant managers, police chiefs, and union bargaining committees typically evaluate these three patterns across consecutive-shift fatigue, turnaround rest hours, and weekend equity:

Operational Metric Pitman (Fixed 2-2-3) Panama (Slow Rotating) DuPont (28-Day Cycle)
Full Cycle Length 14 days (fixed shift) 28 days (14d Day / 14d Night) 28 days (4-stage rotation)
Day/Night Transitions 0 per cycle (bid-based) 2 flips per 28 days 4 flips per 28 days
Max Consecutive Shifts 3 shifts (36 hours) 3 shifts (36 hours) 4 shifts (48 hours)
Shortest Turnaround Gap 60 clock hrs (2 off days) 72–84 clock hrs across flip 48 clock hrs (1 calendar day D→N)
Longest Off-Duty Block 3 days (every 14 days) 3 days (every 14 days) 7 consecutive days (every 28 days)
3-Day Weekends Off Every other weekend (26/yr) Every other weekend (26/yr) 2 full Fri–Sun weekends / 28d (Fri start)
Primary US Sectors Law enforcement, 911, healthcare Semiconductor fabs, DoD, utilities Refineries, chemical plants, paper mills

3. 28-Day Crew Sequence & Statutory FLSA Overtime Math

Under the Fair Labor Standards Act (29 CFR § 778.105), non-exempt overtime must be calculated inside a fixed, recurring 168-hour (7-day) workweek. How an employer defines that 168-hour boundary dramatically alters built-in overtime liability across all three schedules—even though total 28-day work hours remain fixed at 168 hours per crew.

On a 2-2-3 Pitman or Panama pattern where the 3-shift weekend runs Friday–Saturday–Sunday (Mon–Tue On, Wed–Thu Off, Fri–Sat–Sun On), an unaligned Monday-through-Sunday payroll week packs 5 shifts (60 hours → 20 hours OT) into Week 1 and leaves 2 shifts (24 hours → 0 hours OT) in Week 2. By defining the statutory workweek as Sunday 06:00 through Sunday 05:59 (splitting Sunday onto Week 2), HR converts the cycle into 48 hours (Mon, Tue, Fri, Sat = 8 hours OT) and 36 hours (Sun, Wed, Thu = 0 hours OT). Similarly, on DuPont, starting the 4-shift weekend block on Friday while anchoring the statutory workweek on Monday 06:00 yields the exact same 48h / 36h / 48h / 36h profile:

Schedule & Statutory Workweek Boundary Week 1 Week 2 Week 3 Week 4 28-Day FLSA OT
Pitman / Panama (Unaligned Mon–Sun Week) 60h (20h OT) 24h (0h OT) 60h (20h OT) 24h (0h OT) 40 hrs OT
Pitman / Panama (Optimized Sun–Sat Week) 48h (8h OT) 36h (0h OT) 48h (8h OT) 36h (0h OT) 16 hrs OT
DuPont (Unaligned Cycle-Day-1 Week) 48h (8h OT) 72h (32h OT) 48h (8h OT) 0h (0h OT) 48 hrs OT
DuPont (Friday Cycle Start + Mon 06:00 Week) 48h (8h OT) 36h (0h OT) 48h (8h OT) 36h (0h OT) 16 hrs OT

Verify how your 36-hour and 48-hour weeks map onto 26 annual paydays using our 2026 Biweekly Payroll Calendar. Under the Sunday-start statutory split (4 shifts = 48h in Week 1; 3 shifts = 36h in Week 2), every biweekly paycheck stabilizes at 84 paid hours (76 regular + 8 overtime), saving 24 overtime hours per crew every 28 days compared to an unaligned workweek.

4. Circadian Ergonomics, Turnaround Rest & Industry Fit

When to Choose Pitman

Municipal police departments, 911 dispatch centers, and hospital respiratory units favor Pitman because senior staff can bid onto permanent day shifts while newer hires cover nights—eliminating mid-month circadian resets and capping consecutive shifts at three.

When to Choose Panama

Semiconductor wafer fabs, power grid control rooms, and military watch floors choose Panama when every crew needs identical cross-training and Daytime engineering interaction. Flipping only once every 14 days across a 2- or 3-day weekend break allows partial circadian stabilization.

When to Choose DuPont

Petrochemical refineries, chemical plants, and pulp mills favor DuPont because process operators overwhelmingly prize the monthly 7-day continuous break—provided safety protocols manage fatigue during the 4th consecutive night shift and the single-day Day-to-Night turnaround.

Vacation PTO Efficiency Tip: On both Pitman and Panama, taking just 2 shifts (24 hours) of PTO on the mid-week Wednesday–Thursday work block connects both adjacent 2-day and 3-day breaks into a 7-day week off. On DuPont (explored in depth in our DuPont 12-Hour Schedule Guide), taking 4 shifts (48 hours) of PTO on the 4-Day block links 3 Off + 4 PTO + 7 Off into 14 consecutive days off.

Preview & Export Any 12-Hour Rotation

Compare crew start dates side-by-side and download ICS or CSV schedules for Pitman, Panama, DuPont, or custom patterns.

Editorial Review & Verification

Authored & reviewed by the WCalendar Operations & Payroll Editorial Team

Last verified: November 2026 8 min read

Official Standards & Statutory References

Operational Notice: Schedule calculations, statutory citations, and pay-period rules are provided for planning and educational reference. Employer policies, state labor statutes, and collective bargaining agreements (CBAs) may establish stricter rules—always confirm binding dates with your HR or payroll department.

Frequently asked questions

Do Pitman, Panama, and DuPont schedules all average 42 hours per week?
Yes. All three systems divide 672 continuous operational hours across a 28-day macro cycle equally among four crews. Each crew works exactly 14 twelve-hour shifts (168 hours) per 28 days, averaging 42.0 hours per week and 2,190 hours per 365-day year.
What is the exact difference between the Pitman and Panama shift schedules?
Both use the identical 2-2-3-2-2-3 workday rhythm (work 2, off 2, work 3, off 2, work 2, off 3). On a classic Pitman schedule, squads remain on fixed Day or Night shifts (or rotate only at quarterly shift bids). On a Panama schedule, squads flip between Day shifts and Night shifts every 14 days, completing a full rotation every 28 days.
Which 12-hour schedule offers the longest scheduled break without using PTO?
The DuPont schedule provides a built-in 7-consecutive-day break once every 28 days without deducting any vacation hours. By contrast, the longest scheduled break on both Pitman and Panama schedules is a 3-day weekend (Friday through Sunday) every 14 days.
Why does the DuPont schedule require more fatigue tolerance than Pitman or Panama?
To carve out a 7-day monthly break while keeping total workdays at 14 per 28 days, DuPont compresses shifts into two 4-shift (48-hour) blocks and two 3-shift (36-hour) blocks, flipping between days and nights four times per cycle—including a single calendar turnaround day off between 3 Day shifts and 3 Night shifts.
Which schedule costs employers the least in built-in FLSA overtime?
When properly aligned with a Monday statutory workweek boundary, all three schedules produce the exact same federal overtime profile: two 36-hour weeks (0 overtime hours) and two 48-hour weeks (8 overtime hours each), totaling 16 hours of FLSA overtime per crew every 28 days.